CCO tower crane practice test

Tower crane is its own CCO program with its own written exam. You do not need the mobile crane core exam to sit it.

$210written fee
$70practical fee
B30.3main standard

20 Tower crane practice questions with answers

Pick an answer to see whether you were right and why. Reviewed November 2026. No sign-up.

Not started20 to go
  1. Tower Crane

    1.On an inner-outer tower crane, how is the jib supported?

    Show answer

    Answer: B. By a partial slewing inner tower that rotates inside a fixed outer tower. The inner-outer design supports the jib on a partially slewing inner tower that turns inside a stationary outer tower.

  2. Tower — Erection & Structure

    2.According to ASME B30.3, alterations or modifications to a tower crane shall be:

    Show answer

    Answer: A. Performed by or approved by the manufacturer or, in its absence, a qualified person. Alterations or modifications shall be performed by or approved by the manufacturer or, in the absence thereof, a qualified person, and must comply with the volume with records kept.

  3. Tower — Operations

    3.Rail clamps on a traveling tower crane shall NOT be used for what purpose?

    Show answer

    Answer: C. To restrain tipping of the crane. Rail clamps hold against travel/wind but shall not be used as a means of restraining tipping of a crane.

  4. Tower Crane

    4.In ASME B30.3, a freestanding tower crane is one that is:

    Show answer

    Answer: A. Supported on a foundation or structural support without braces, guys, or other means. A freestanding tower crane is supported on a foundation or structural support without assistance from braces, guys, or other means.

  5. Tower — Erection & Structure

    5.Unless provisions to secure the swing are approved by the manufacturer, how must a tower crane be configured when placed out of service?

    Show answer

    Answer: C. Free to weathervane. Out of service the crane shall be configured to weathervane, exposing minimal surface area to the wind.

  6. Tower — Operations

    6.Why must the operator avoid landing (setting down) the hook block?

    Show answer

    Answer: B. The rope goes slack and can spool incorrectly on the drum. Landing the hook block creates slack rope, which can wind loosely or incorrectly onto the hoist drum.

  7. Tower Crane

    7.On a tower crane capacity chart that lists several boom or jib lengths, how does the rated capacity at a given radius change as the fitted boom gets longer?

    Show answer

    Answer: D. It decreases. At any radius shared by two columns, the longer boom is rated lower — the extra boom weight and leverage eat into the available moment. Capacity also falls steadily as radius increases within any single column.

  8. Tower — Erection & Structure

    8.For backward stability, ASME B30.29 requires that an unloaded self-erecting crane exposed to unfavorable in-service wind plus an upward force at the trolley or jib tip equal to what value shall not tip backward?

    Show answer

    Answer: D. 30% of the rated load at any operating radius. Backward stability requires that the unloaded crane, under unfavorable in-service wind plus an upward force at the jib tip equal to 30% of the rated load at any radius, shall not tip over backward.

  9. Tower — Operations

    9.A tower crane is operated by remote control rather than from a cab. Where must the load rating chart be located?

    Show answer

    Answer: A. Attached to the remote control console. Every tower crane must have a load chart where the operator works — in the cab, or attached to the control console on a remote-controlled machine.

  10. Tower Crane

    10.Which practice is prohibited when operating a tower crane?

    Show answer

    Answer: A. Using crane motions to drag a load that is not freely suspended. Horizontal displacement of loads that are not freely suspended is forbidden, as are pulling loads at an angle and pulling off fixed loads.

  11. Tower — Erection & Structure

    11.The plan for a self-erecting tower crane should be divided into which two major sections?

    Show answer

    Answer: A. Delivery, set-up, erection, and dismantle; and lifting operations. Planning splits into (1) delivery, set-up, erection, and dismantle and (2) lifting operations.

  12. Tower — Operations

    12.Load limit device settings are verified by a static test using test loads of what percentage of the applicable rating?

    Show answer

    Answer: D. 102.5 to 110 percent. Load limit device settings are verified by static testing at 102.5 to 110 percent of the applicable rating.

  13. Tower — Ropes & Hooks

    13.On a hammerhead tower crane, what is the "trolley rope"?

    Show answer

    Answer: D. The rope that pulls the trolley in and out along the jib. The trolley rope (traverse rope) moves the trolley along the jib; the hoist rope raises and lowers the load.

  14. Tower Crane

    14.What is the minimum pitch diameter for load hoist sheaves on a tower crane, expressed as a multiple of the rope's nominal diameter?

    Show answer

    Answer: B. 18 times the rope diameter. Load hoist and load block sheaves require a minimum pitch diameter of 18 times the rope diameter; boom hoist sheaves require 15.

  15. Tower — Erection & Structure

    15.Tie-ins shall be designed and anchored to the host structure to resist what?

    Show answer

    Answer: A. The horizontal forces applied in any direction. Tie-ins must resist the horizontal forces applied in any direction as specified by the manufacturer or qualified person.

  16. Tower — Operations

    16.How does a tower crane's slewing drive brake behave in high wind?

    Show answer

    Answer: B. It holds below the design wind velocity but slips above it, allowing the crane to weathervane. Deliberate slip above the design wind velocity relieves the slew drive and lets the crane turn downwind rather than tearing the slew ring apart.

  17. Tower — Ropes & Hooks

    17.What is "birdcaging" in a wire rope?

    Show answer

    Answer: D. Strands separating and bulging outward from the core in a cage shape, usually from sudden load release or torsional unbalance. Birdcaging is strand distortion where outer strands open away from the core; it is cause for rope removal.

  18. Tower Crane

    18.In what sequence are counter-jib counterweight blocks installed on a tower crane?

    Show answer

    Answer: B. Starting at the rear, farthest point from the tower, working inward. The blocks must be placed across the opening beginning at the point farthest from the tower, and their correct verified weight must be maintained.

  19. Tower — Erection & Structure

    19.A self-erecting tower crane is MOST vulnerable to wind during which activity?

    Show answer

    Answer: C. Unfolding and folding. Trap: superlative plus a seductive distractor — weathervaning is the crane's wind SURVIVAL mode, not its weak moment; the vulnerable window is unfolding and folding, which is why those operations are wind-limited.

  20. Tower — Operations

    20.What safety equipment does every tower crane require, and what is required along its jib for the operator's reference?

    Show answer

    Answer: A. A fire extinguisher on the crane and radius markers installed along the jib. Every tower crane requires a fire extinguisher, and radius markers should be installed on the jib so the operator can read the load radius.

What the Tower crane exam covers

  • Erection, climbing and dismantling
  • Tie-ins and foundations
  • Weathervaning and wind limits
  • Trolley, hook block and hoist rope
  • Load limit devices and testing
  • Tower crane capacity charts

Fees from the CCO fee schedule.

Study the whole Tower crane exam

5,000+ practice questions across core and every specialty, timed practice exams, a load chart trainer and audio lessons. One payment of $197 covers 12 months.

Tower crane exam questions

Do I need the mobile crane core exam for tower crane?

No. Tower crane operator is a separate CCO program with its own written exam and practical.

What does CCO tower crane certification cost?

CCO lists $210 for the tower crane written exam and $70 for the practical.

Which standard do tower crane questions come from?

Mostly ASME B30.3 for tower cranes, along with OSHA 29 CFR 1926 Subpart CC. Self-erecting tower cranes fall under ASME B30.29.

Are these the real CCO exam questions?

No. CCO does not publish its exam questions. These are original practice questions on the same tower crane topics, each with the rule or reason behind the answer.