CCO lattice boom (LAT) practice test

Lattice boom cranes are built up from pinned boom sections. CCO certifies crawler and truck-mounted lattice cranes under one designation, LAT.

28questions
60 mintime limit
Yescalculator
$80written fee

20 Lattice boom (LAT) practice questions with answers

Pick an answer to see whether you were right and why. Reviewed November 2026. No sign-up.

Not started20 to go
  1. Lattice Boom — Load Charts

    1.A crane with 120 ft boom will be operating at a 43 ft radius. The load chart shows an entry indicating 25,000 lbs at a 40 ft radius, followed immediately by an entry listing 20,000 lbs at a 45 ft radius. What is the crane's capacity at the 43 ft radius?

    Show answer

    Answer: A. 20,000 lbs. When the working radius falls between chart radii, use the next longer listed radius: 43 ft falls between 40 and 45, so use the 45-ft entry — 20,000 lbs.

  2. Lattice Boom — General

    2.Before a lattice crane lifts its own counterweight, which conditions must be met?

    Show answer

    Answer: D. Firm level ground, gantry fully extended, and four parts of load line reeved on a basic boom. Counterweights are heavy and the pick is made at short radius on the basic boom, so parts of line and a fully extended gantry are both required. Counterweight is normally connected before the complete boom is installed, and set on hardwood blocking when off.

  3. Lattice Boom — Load Charts

    3.Which of the following is NOT considered part of the main boom load on a lattice crane?

    Show answer

    Answer: D. The crane counterweight. Trap: NOT stem — everything suspended beneath the boom and jib point sheaves counts as load; the counterweight is on the other end of the machine entirely.

  4. Lattice Boom — General

    4.A pin connected lattice boom is being dismantled. After connecting pendants at the maximum cantilever point and lifting the boom slightly off the ground, the next step is to remove the:

    Show answer

    Answer: A. lower connection pins located at and ahead of the pendants. With the boom suspended by the pendants, only the lower pins at and ahead of the pendant attachment point are removed first — never pins behind the pendants.

  5. Lattice Boom — General

    5.Ground bearing pressure under a crawler is highest when the load is over the:

    Show answer

    Answer: C. corner (end of one track). Over a track corner the load concentrates at the end of one track, producing the highest ground bearing pressure.

  6. Lattice Boom — General

    6.A lattice boom section is found with a visibly bent chord and cracked lacing. The correct action is to:

    Show answer

    Answer: A. remove the section from service until evaluated by the manufacturer or a qualified person. A lattice boom carries load through its chords and lacing; a bent chord or cracked lacing can trigger sudden buckling, so the section must be removed and evaluated, not field-repaired.

  7. Lattice Boom — General

    7.During disassembly, the boom projecting beyond its last suspension (pendant) point is called the:

    Show answer

    Answer: C. cantilever length. The cantilever length is the portion of boom projecting beyond the pendant attachment while it is suspended.

  8. Lattice Boom — General

    8.When disassembling a pinned lattice boom, you must never remove a pin on any section located:

    Show answer

    Answer: B. between the pendant attachment point and the crane. The sections between the pendants and the crane support the suspended boom; pulling a pin there lets the boom fall.

  9. Lattice Boom — General

    9.On lattice boom friction cranes fitted with a controlled load lowering device, a heavy load should be lowered by using the:

    Show answer

    Answer: B. controlled load lowering and the brake. A heavy load on a friction crane should be lowered under power using the controlled load lowering device together with the brake, rather than slipping the brake alone.

  10. Lattice Boom — General

    10.Blocking placed under the ends of the crawler tracks during long-boom erection:

    Show answer

    Answer: D. moves the tipping fulcrum forward and increases stability. Blocking under the track ends (per procedure) shifts the fulcrum forward and adds stability while raising a long boom off the ground.

  11. Lattice Boom — General

    11.During assembly of a lattice truck crane, the outriggers must be set to:

    Show answer

    Answer: D. take the equipment's weight off the wheels. The outriggers must support the crane, removing weight from the wheels, before the boom is assembled.

  12. Lattice Boom — General

    12.On a lattice crane, boom angle relative to operating radius is best described as:

    Show answer

    Answer: B. an indication only — the operating radius governs capacity. Boom angle indicates radius, but in all cases the actual operating radius governs the rated capacity.

  13. Lattice Boom — General

    13.When assembling a lattice boom on most crawler cranes, using inserts of different lengths, which insert section should be closest to the boom foot?

    Show answer

    Answer: A. 10 ft. Manufacturers generally require the shortest insert closest to the boom foot, with progressively longer inserts farther out, per the boom makeup chart.

  14. Lattice Boom — General

    14.Crawler crane capacities are typically based on what percentage of the tipping load?

    Show answer

    Answer: C. 75%. Crawler ratings use 75% of tipping, versus 85% for carrier-mounted cranes on outriggers.

  15. Lattice Boom — General

    15.If a loaded lattice boom contacts the load or rests on an obstruction, the greatest risk is that the boom will:

    Show answer

    Answer: B. buckle and collapse from off-axis loading. A lattice boom is designed for axial load only; side or bearing loads it was never designed for can buckle it.

  16. Lattice Boom — General

    16.Pendants (pendant straps) on a lattice crane are:

    Show answer

    Answer: D. standing rope that supports the boom and is inspected for broken wires, especially at end connections. Pendants are fixed-length standing rope suspending the boom from the gantry/mast; being standing rope they use stricter inspection criteria and are checked closely at their end fittings.

  17. Lattice Boom — General

    17.A correct statement about installing a pin connected lattice boom on a mobile crane, is that the:

    Show answer

    Answer: D. boom hoist pawl should be used during the installation. During installation the boom hoist drum pawl should be engaged so the boom cannot lower if the brake slips; never work under an unsupported boom.

  18. Lattice Boom — General

    18.The far-right control lever in the ASME B30.5 standard conventional-crane arrangement operates the:

    Show answer

    Answer: C. boom hoist, which must hold when released to center. Releasing the boom hoist lever to center must automatically hold the boom stationary.

  19. Lattice Boom — General

    19.A jib erected on a lattice boom but NOT used for the lift is deducted at:

    Show answer

    Answer: B. its effective weight (larger than actual). An erected-but-unused jib deducts at an effective weight exceeding its actual weight because of its leverage out at the boom point.

  20. Lattice Boom — General

    20.During DISASSEMBLY, with the boom suspended by the pendants and lifted slightly off the ground, which pins may be removed first?

    Show answer

    Answer: B. The lower connection pins located at and ahead of the pendant attachment points. Trap: ahead-versus-behind reversal — every section between the pendants and the crane is load-bearing, so only the LOWER pins at and ahead of the pendants come out first; pulling pins behind the pendants drops the boom.

What the Lattice boom (LAT) exam covers

  • Boom assembly and pin removal order
  • Pendants and cantilever limits
  • Crawler ground bearing pressure
  • Counterweight handling
  • Tipping and structural limits on the chart
  • Boom hoist and load lowering controls
ExamQuestionsTimeCalculatorFee
Core written (all mobile cranes)9590 minNo$140
LAT specialty written2860 minYes$80
LAT practical———$70

Exam format from the CCO Mobile Crane Operator Candidate Handbook. Fees from the CCO fee schedule.

Study the whole Lattice boom (LAT) exam

5,000+ practice questions across core and every specialty, timed practice exams, a load chart trainer and audio lessons. One payment of $197 covers 12 months.

Lattice boom (LAT) exam questions

How many questions are on the CCO LAT written exam?

28 questions with a 60-minute limit, and a calculator is allowed. To earn the LAT designation you also pass the 95-question core exam and the LAT practical.

What does the LAT written exam cover?

Four areas: site (about 23%), operations (about 23%), technical knowledge (about 19%) and load charts (about 35%). The load chart problems use the manufacturer charts handed out with the exam.

What does the LAT exam cost?

CCO lists $80 for the LAT written exam and $70 for the LAT practical, plus $140 for the core written exam if you have not passed it.

What happened to the LBC and LBT codes?

CCO folded the lattice boom crawler (LBC) and lattice boom truck (LBT) codes into a single lattice boom designation, LAT. Older cards may still show LBC or LBT.

Are these the real CCO exam questions?

No. CCO does not publish its exam questions. These are original practice questions on the same lattice boom topics, each with the rule or reason behind the answer.