CCO core exam practice test
Every mobile crane operator sits the core exam, whatever crane they run. It is 95 questions in 90 minutes with no calculator, so pace matters as much as knowledge.
20 Core practice questions with answers
Pick an answer to see whether you were right and why. Reviewed November 2026. No sign-up.
-
Operations
1.When correcting circle or diagonal drift, the operator should compensate…
Show answer
Answer: D. One function at a time — first the side-to-side swing drift, then the in-and-out boom drift. Circle and diagonal drift are corrected one component at a time, eliminating swing drift before boom drift.
-
Mobile Crane Essentials
2.What is the design safety factor for rotation resistant ropes?
Show answer
Answer: D. 5 to 1. Rotation resistant ropes are rated at 5 to 1 (10 to 1 when hoisting personnel).
-
Standards
3.Which of the following OSHA regulations govern suspended personnel platforms?
Show answer
Answer: B. OSHA 1926.1431. OSHA 1926.1431 covers hoisting personnel with cranes/derricks.
-
OSHA 1926 Subpart CC
4.According to OSHA 1926.1408 Table A, the minimum clearance distance for power lines over 350 kV up to 500 kV is:
Show answer
Answer: B. 25 feet. Table A requires 25 feet for lines over 350 to 500 kV.
-
ASME B30.5 (Mobile Cranes)
5.According to ASME B30.5, a boom hoist disconnect, shutoff, or hydraulic relief shall be provided to automatically stop the boom hoist when:
Show answer
Answer: A. The boom reaches a predetermined high angle. Para 5-1.9.1(d) requires the device to automatically stop the boom hoist when the boom reaches a predetermined high angle.
-
Standards & Violations
6.Outriggers at mid-extend give you…
Show answer
Answer: B. Reduced capacity — use the mid-extend chart. Mid-extend has its own chart with reduced ratings. Never interpolate between outrigger configurations.
-
Definitions
7.'Weathervaning' is defined as:
Show answer
Answer: A. Releasing the swing brakes to allow wind-induced rotation of the superstructure when out of service. Weathervaning releases the swing brakes so the out-of-service superstructure rotates with the wind, exposing minimal surface area.
-
Crane Types
8.The location of a crawler crane's tipping axis depends on whether the…
Show answer
Answer: B. Track rollers are inline with or offset from the sprocket and idler. The tipping axis of a crawler crane depends on whether the track rollers are inline or offset from the sprocket and idler.
-
General Knowledge
9.When a fixed jib is installed on a crane, its primary purpose is to:
Show answer
Answer: A. Increase the total height a load may be lifted. A fixed jib extends the boom tip, primarily to increase the height to which a load can be lifted.
-
Wire Rope
10.A standing rope (such as a boom pendant) must be removed from service at how many broken wires in one rope lay?
Show answer
Answer: D. 3. Standing (non-moving) rope is retired at 3 broken wires in one lay, or 2 broken wires at an end connection.
-
Pitch Diameter
11.Under ASME B30.5, the load hoist DRUM must provide a first-layer pitch diameter of at least:
Show answer
Answer: B. 18 times the nominal rope diameter. The load hoist drum requires a first-layer pitch diameter of not less than 18 times the nominal rope diameter, gentler than the 15x boom drum.
-
Load Calculation
12.How do you find the weight of a fabricated structural steel assembly such as a beam-and-plate weldment?
Show answer
Answer: A. Calculate the weight of each part and add them, or look up the weight per lineal foot of each shape in a steel data book. Treating a shape as a solid block grossly overstates its weight; the accepted methods are to break it into parts and total them, or to use published weights per lineal foot for the standard shape.
-
Load Charts
13.Load chart capacities are determined by manufacturers using what principle?
Show answer
Answer: B. Leverage — balancing moments on each side of a fulcrum. Manufacturers use the principles of leverage, balancing load moment against crane moment, then apply the 85 or 75 percent stability margins.
-
Power Lines
14.A crane is considered to be working near a power line rated over 350 kV when any part of it CAN reach within what distance?
Show answer
Answer: C. 50 feet. The encroachment rules apply when the crane, load line, load, or rigging can reach within 20 feet of lines up to 350 kV or 50 feet of lines over 350 kV.
-
Operation Aids
15.Which of these is a required SAFETY DEVICE under Subpart CC, rather than an operational aid?
Show answer
Answer: B. Horn. The horn, crane level indicator, boom stops, jib stops, brake locks, jack check valves, and rail clamps/stops are safety devices; LMIs, ATBs, and indicators are operational aids.
-
Operations
16.Instead of getting the load weight from a recognized source, an operator may begin hoisting and use the LMI to check whether the load exceeds…
Show answer
Answer: D. 75 percent of the maximum rated capacity at the longest radius to be used. If the indicator shows the load exceeds 75 percent of maximum rated capacity at the longest radius of the lift, the operator must stop and verify the actual weight before proceeding.
-
Standards
17.In the ASME B30 standards, the word 'should' indicates…
Show answer
Answer: D. A recommendation whose advisability depends on the situation. 'Should'/'may' marks a recommendation whose advisability depends on the facts; only 'shall'/'must' is mandatory.
-
OSHA 1926 Subpart CC
18.According to OSHA 1926.1420, devices used to transmit signals electronically must be:
Show answer
Answer: A. Tested on site before beginning operations to ensure the signal transmission is effective, clear, and reliable. 1926.1420(a) requires on-site testing of signal transmission devices before beginning operations.
-
ASME B30.5 (Mobile Cranes)
19.According to ASME B30.5, an example of a commonly accepted critical lift criterion is:
Show answer
Answer: B. The lifting operation involves more than one crane lifting a common load with shared loading. Appendix A-1 lists multicrane shared-load lifts, lifted loads exceeding a predetermined percentage of chart capacity, personnel lifting, unique or irreplaceable items, and lifts within a boom length of power lines among common critical lift criteria.
-
Definitions
20.The purpose of an auxiliary boom point (rooster) sheave is to…
Show answer
Answer: A. Keep the main hoist line and the whip line separated. The rooster sheave is a short single-sheave extension that keeps the main hoist line and the auxiliary/whip line separated.
You scored
That was 20 core questions. The app has the full bank, tracks every miss and brings it back until you have it.
What the Core exam covers
- Power line clearances under OSHA 1926.1408
- Ground conditions, blocking and outriggers
- Standard hand and voice signals
- Wire rope and sheave inspection
- Operational aids and safety devices
- Load chart reading and deductions
| Domain | Share of exam | What it tests |
|---|---|---|
| Site | 22% | Ground conditions, setup, power line clearances, site hazards |
| Operations | 28% | Signals, controls, safe operating practice, rigging |
| Technical knowledge | 23% | Crane components, wire rope, inspections, standards |
| Load charts | 27% | Reading charts, deductions, radius and capacity |
Approximate weights from the CCO Mobile Crane Operator Candidate Handbook. Fee from the CCO fee schedule.
Study the whole Core exam
5,000+ practice questions across core and every specialty, timed practice exams, a load chart trainer and audio lessons. One payment of $197 covers 12 months.
Core exam questions
How many questions are on the CCO core exam?
The mobile crane core written exam has 95 multiple-choice questions and a 90-minute limit, which is just under a minute per question.
Can I use a calculator on the core exam?
No. Calculators are not allowed on the core exam. They are allowed on the 28-question specialty exams, where most of the load chart arithmetic sits.
Do I have to pass core before a specialty exam?
You can sit them together. To earn a designation you pass core, one specialty written exam and the matching practical within 12 months of your first passed exam.
What score do I need to pass?
CCO does not publish a percentage cut score for its written exams. A sensible target is 80% or better on every topic in practice before you book.
Are these the real CCO exam questions?
No. CCO does not publish its exam questions. These are original practice questions on the same mobile crane topics, each with the rule or reason behind the answer.