1.The extendable legs that provide the stability base on a truck-mounted loader crane are called:
Show answer
Answer: A. stabilizers (outriggers). Stabilizers (outriggers) extend out and down to widen the support base and take load off the truck springs, providing stability for the lift.
-
Articulating — Load Charts
2.An articulating crane with a winch is at full line payout. Per the manufacturer, how many full wraps must remain on the drum?
Show answer
Answer: B. At least 2 full wraps (some manufacturers require 3). The rope anchor alone is not designed to hold the load — ASME B30.5 and manufacturer charts require a minimum of two full wraps remaining on the drum at all times; some manufacturers specify three. Always check your chart’s notes.
-
Articulating Crane
3.The purpose of the boom rest/cradle on the truck body is to:
Show answer
Answer: D. support and secure the folded boom during travel. The cradle supports and secures the stowed boom for travel so it does not bounce, shift, or fatigue the structure on the road.
-
Articulating Crane
4.Hydraulic hoses on an articulating crane should be inspected for:
Show answer
Answer: D. cracks, bulges, chafing, and leaks. Cracked, bulging, chafed, or leaking hoses can burst under pressure and cause loss of control or load-holding, so they must be inspected and replaced as needed.
-
Articulating Crane
5.An operator using radio remote control on an articulating crane should always:
Show answer
Answer: D. stand clear of the load and boom with a full view of the work, never underneath. Radio-remote operation lets the operator move to the safest vantage point; the operator must keep clear of the load and boom, never standing beneath a suspended load.
-
Articulating Crane
6.If a hydraulic cylinder on an articulating crane drifts down slowly under load, the likely concern is:
Show answer
Answer: D. a failing load-holding valve or cylinder seal that must be repaired before use. Cylinder drift indicates a leaking load-holding valve or worn seal that can let a load fall; the crane must be taken out of service and repaired.
-
Articulating Crane
7.As the horizontal outreach of an articulating crane increases, the rated capacity:
Show answer
Answer: C. decreases. Capacity is governed by load moment (weight times outreach), so the farther the load is from the column, the less the crane can safely lift.
-
Articulating Crane
8.Before extending the stabilizers, the operator should:
Show answer
Answer: C. make sure the area around each stabilizer is clear of people and obstructions. Deploying stabilizers can strike or crush anyone in their path, so the area must be checked and cleared before extension.
-
Articulating Crane
9.If an articulating crane's overload warning activates during a lift, the operator should:
Show answer
Answer: A. stop and reduce the load moment by bringing the load in or setting it down. An overload signal means the load moment is at or over the limit; the operator must reduce it by decreasing reach or landing the load, never override and continue.
-
Articulating Crane
10.Wind acting on a suspended load handled by an articulating crane can:
Show answer
Answer: A. increase the effective radius and side-load the boom. Wind pushes the load, increasing radius and imposing side loads on the boom; the operator must account for wind, which the chart does not include.
-
Articulating Crane
11.Load-holding (counterbalance) valves on an articulating crane's cylinders mainly:
Show answer
Answer: D. hold the load in place if a hydraulic hose or line fails. Load-holding valves trap oil in the cylinder if a hose or line ruptures, preventing the boom or load from dropping.
-
Articulating Crane
12.A frequent cause of articulating-crane accidents is:
Show answer
Answer: A. overloading at long outreach and unstable setup on soft or unlevel ground. Exceeding the moment rating at long reach and setting up on soft or unlevel ground are leading causes of tip-overs and structural failures.
-
Articulating Crane
13.The point about which an articulating crane would tip is the:
Show answer
Answer: B. outer edge of the support base formed by the stabilizers and mounting. Tipping occurs about the outer edge of the support base; a load moment that exceeds the stabilizing moment about that line overturns the crane.
-
Articulating Crane
14.The best way to gain capacity for a load that is slightly too heavy at the planned position is to:
Show answer
Answer: A. reduce the outreach by handling the load closer to the column. Reducing outreach shortens the load-moment arm and raises rated capacity; extending the boom would do the opposite.
-
Articulating Crane
15.Compared with a telescopic crane of similar size, an articulating loader crane generally:
Show answer
Answer: D. is faster for repeated loading/unloading and better at reaching over obstacles. Loader cranes are optimized for quick, repetitive loading and reaching around obstacles, trading some straight-line reach and heavy capacity for that folding versatility.
-
Articulating Crane
16.Most modern articulating cranes provide continuous slewing (rotation) by means of:
Show answer
Answer: D. a rack-and-pinion or slewing gear at the base column. The base column rotates on a slewing gear (often rack-and-pinion or a worm/ring gear), giving powered and sometimes continuous rotation.
-
Articulating Crane — Core
17.On a graded (sloped) surface, wheel chocks on a truck-mounted articulating crane should be placed:
Show answer
Answer: D. Snug against the tires on the downhill side to prevent the carrier from rolling. Chocks resist rolling; on a grade they must block movement in the downhill direction.
-
Articulating Crane
18.The minimum clearance requirements from energized power lines for an articulating crane are:
Show answer
Answer: D. the same as for other cranes, applying to the boom, load line, and load. Power-line clearance rules apply to any crane; the operator, including a remote operator on the ground, must keep the boom, load line, and load outside the minimum approach distance.
-
Articulating Crane — Core
19.Before driving a truck-mounted articulating crane away from a set-up, the operator must:
Show answer
Answer: D. Stow the boom, retract and secure the stabilizers, and disengage the PTO. The boom is stowed, stabilizers retracted and secured, and the PTO disengaged before road travel.
-
Articulating Crane
20.A pre-use inspection of an articulating crane should include checking the hydraulic system for:
Show answer
Answer: D. leaks at hoses, fittings, and cylinders. Hydraulic leaks at hoses, fittings, and cylinder rods signal wear or damage that can lead to loss of load-holding and must be corrected before use.
You scored
That was 20 articulating crane questions. The app has the full bank, tracks every miss and brings it back until you have it.
What the Articulating crane exam covers
- Stabilizer setup and support
- Outreach and rated capacity
- Load-holding valves and hydraulics
- Remote control operation
- Stowing the boom for travel
- Pre-use inspection
Fees from the CCO fee schedule, which lists the same fees for the articulating boom loader, articulating boom crane and articulating boom crane with winch.
Study the whole Articulating crane exam
5,000+ practice questions across core and every specialty, timed practice exams, a load chart trainer and audio lessons. One payment of $197 covers 12 months.
Articulating crane exam questions
What is an articulating boom crane?
A crane whose boom folds at hinged sections, like a knuckle. Most are mounted on a truck behind the cab and used to deliver and place material.
What does CCO articulating crane certification cost?
CCO lists $210 for each articulating crane written exam and $70 for each practical.
Are these the real CCO exam questions?
No. CCO does not publish its exam questions. These are original practice questions on the same articulating crane topics, each with the rule or reason behind the answer.